Project History

Past Projects

Alcatel-Lucent “Blue Sites” project 2014
Installation of UMTS 850 and 1900 Macrocell Components to ALU macro cabinets (9391) for AT&T
Amps, Filters, Radios, splitters/combiners and jumpers. Weather proofing for Coax
Commissioning of with ALU RMT licensed software, integrated and call tested carrier adds

Alcatel-Lucent “Red Sites” project 2014-2015
Installation and Integration of ALU 7705 SAR-8 SIADs
Turned up and connected via T1s or fiber
Installation of UMTS NodeBs and LTE eNodeBs (9926) with RRHs
Full rack and stack - grounding, power, backhaul, sector fibers, alarms, GPS lines
As needed: T1 installation from street to site. Troubleshot NIU issues with AT&T transport team when necessary
Commissioned with ALU licensed software (IcET, NEM, RMT)
Integration using both scripts manual commissioning using EDP, RFDS, and CIQ documents
Utilized AOTS CR Tool to manage conflicts prior to go/no go for hot swap and full site migrations
Standard, VoLTE, e911, and drive testing
NEA testing and certification with AT&T internal and external alarms
Customer facing and responsible for status and Issues/Action to market leadership
Utilized AT&T TP-76300 guidelines for all labeling and installation procedures and self-performed audits on completed sites.

DAS projects 2015 – 2018
Responsible for scheduling and perfoming the commissioning, Integration, call & NEA testing, and provided Site Acceptance support for turn up procedures with AT&T/T-Mobile owned or third party owned DAS systems using Alcatel-Lucent hardware (9926 NodeB and eNodeB) with ALU software and MOPs, as well as Nokia software on new Airscale Platform (FSM4)
Commissioning and integration of ALU 7705 SIADs using AT&T ACAT software and work orders provided by AT&T
e911 compliance on all sites completed directly with AT&T e911 teams
Worked nationwide at multiple venues including Secure Facilities, NFL and MLB stadiums, and Entertainment venues
Upward facing and responsible for status and Issues/Action to AT&T market leadership

Audit projects 2015 – 2017
Trained, Lead, and Scheduled over 20 field teams to Perform audits for AT&T nationally
Audits included: Repairs and preventative maintenance of HVAC systems, Generators, Building structures, Grounding Systems, Pest Control Systems, and Yards
Utilized AT&T CTS Mobility system to search site info, issue TT to Field Force for Vendor meets
Utilized AT&T MDAT online database for work details and reporting back to AT&T
Utilized AT&T NSFD team for check in/out procedures and troubleshooting

Nokia Upgrades 2017-2018
Sprint upgrades for 2.5 TDD with new bCAM and bCEM2 equipment and carrier aggregation
Certified on Nokia FSM4 Airscale installation and integration, and worked with Nokia engineering teams to analyze and revise technical site survey methodology to create appropriate site specific MOPs and BOMs
Installation of new Airscale base stations (FSM4), and migration of live sites from existing ALU 9926 platform to FSM4
Full rack and stack - grounding, power, alarms
Migration including commissioning integration of FSM4 base stations and SMMx alarm units, fiber certification, and call testing
Recruited, Trained, Managed, Lead, and served as SME for 30+ teams on project
Customer facing and responsible for status and Issues/Action to Nokia, AT&T, Verizon, and Sprint leadership

Wireless Small Cell site installation 2016-2018
Managed teams and Lead project - Complete site prep including utility permits, surveying, trenching and conduit from fiber drop at street to building fiber entrance. Roof prep to penetrate membrane roof with conduit. Ground and rooftop platform installation. And AC and DC power work, as well as batteries.
Rooftop sleds, wall mounted, and stealth concealment of antennas
All conduit, cabling, fiber, and grounding include new site ground ring installation using CADWELD or equivalent
Antenna and antenna line installation and testing using PIM and SWEEP Anritsu equipment

Verizon infrastructure upgrades 2017
Generator replacement and shelter upgrades, including power and alarm installation, vent and fuel line pipe fitting, and structural support modifications

T-Mobile PPC Replacement Project 2017-2018
Replaced outdated circuit breaker panels with new PPCs with integrated generator plugs
Worked with utility and local electricians to shut down power to site during maintenance windows and changed replaced outdated power with PPC within limited time frame

Raw land site inspection 2017-2018
Customer facing with AT&T representatives, tower construction manager, surveyor, and prospective landlords
Discussed ideal tower placement, measured, marked, and drafted
Flagged in field and tracked via GPS survey equipment to draw up site plan of lease area and site compound footprint
Measured and flagged easements for power and fiber using nearest utility information and locations found in the field

Sprint tower and compound surveys 2017-2018
Compound measurement and CD confirmation, redline sketch of any difference from CD to field
Photographed RAD center from each tower face and multiple angles, Drone photography as needed
Complete rooftop mapping for Fire Marshall in NYC for compliance with NYFD rooftop access